If your non-coal mine needs dry-type step-down power, we build custom KKSG mining dry-type transformers to your input voltage, output voltage, and kVA.
- Built capacities: 20 ratings from 1 to 630 kVA, quoted to your order
- KY certificate examples: KKSG-50/1.2(0.693,0.4) (IP22), KKSG-630/1.2(0.693) (IP21)
- Minimum order starts at 1 unit, with no sample-making fee
- Custom build lead-time guidance is 7–15 days, in wood cases or cartons
- One-year warranty from receipt with remote video and online guidance
Comparing phase options for auxiliary circuits? Read Single-Phase or Three-Phase for Mining Auxiliary Loads? or check our single-phase KKDG for auxiliary loads. You can also browse our full Transformer Product Range.
KKSG Capacities Built (1–630 kVA) and Factory Nameplate Examples
We have built KKSG mining dry-type transformers across 20 capacity ratings from 1 to 630 kVA. Built ratings: 1, 2, 3, 5, 10, 15, 20, 25, 30, 40, 50, 80, 100, 150, 200, 250, 315, 400, 500, and 630 kVA. Exact voltage and capacity pairings are confirmed by model during quotation based on your supply voltage, load voltage, and kVA. Two past KKSG factory nameplates show the fields our plates carry.
| Built unit model | Rated capacity | Input voltage field | Output voltage field | Frequency and connection | Printed certificate number |
|---|---|---|---|---|---|
| KKSG-10KVA | 10 kVA | 380 V | 380 V 220 V | 50–60 Hz, Y/Y | CMExC23.1645 |
| KKSG-30KVA | 30 kVA | 660 V | 380 V | 50–60 Hz, Y/Y | CMExC23.1645 |
Both factory nameplates list Zhejiang Hongmei Electrical Manufacturing Co., Ltd. as manufacturer and specify a Y/Y (three-phase wye/star primary and secondary) winding connection. The KKSG-10KVA nameplate prints 380 V and 220 V side by side in the output field, with no stated capacity split or simultaneous full-load rating. Certificate number CMExC23.1645 is printed on both plates, while certificate coverage follows the models listed on the certificate itself. To check every field during receiving inspection, read How to Read a Mining Transformer Nameplate.
How to Size a Three-Phase KKSG Mining Transformer for Your Load
For a balanced three-phase mining dry-type transformer, steady-state apparent power equals √3 times RMS line voltage times RMS line current, divided by 1,000. Written as an equation: kVA = √3 × V_line × I ÷ 1000. Reversing that gives full-load line current at your secondary voltage: I = kVA × 1000 ÷ (√3 × V_line). For a single-phase auxiliary circuit, drop the √3 factor and use kVA = V × I ÷ 1000 and I = kVA × 1000 ÷ V.
When your equipment list states real power in kW, divide kW by the load power factor using kVA = kW ÷ power factor. Reactive power drawn by inductive loads consumes transformer and feeder capacity alongside real power. Sizing straight from kW undersizes the transformer whenever power factor drops, because required kVA and line current both climb for the same kW output.
Two example calculations show how these formulas work on a balanced three-phase load list. For a balanced three-phase 380 V load drawing 40 A, apparent power is 1.732 × 380 × 40 ÷ 1000 ≈ 26.3 kVA. With a 22 kW load running at a 0.8 power factor, steady-state kVA comes to 22 ÷ 0.8 = 27.5 kVA. Plug your actual voltages, currents, or kW figures into these equations for a steady-state baseline. The balanced three-phase formula assumes equal phase loads, and we’ll review your voltages, power rating, and enclosure requirements during quotation.
Pumps, fans, and other motors draw extra starting current beyond running amps. If your KKSG transformer feeds motors, check startup demand early so you can prepare motor-starting load information before setting capacity. You’ll also find full single-phase and three-phase current tables in How Do You Convert kVA to Single-Phase or Three-Phase Current?.
Where a KKSG Mining Dry-Type Transformer Fits on Site
Our two KKSG mining certificates cover chambers and main roadways in non-coal mines free from dripping water and dust ingress. Both CMExC23.1645 and CMExC24.1859 print that operating location explicitly for their listed models.
Coal mines and zones with flammable gas or combustible coal dust fall outside these two KKSG certificates, which apply to non-coal mines. Sites exposed to dripping water or dust sit outside these certificate limits. Describe your site conditions in your enquiry, and we’ll check whether a KKSG build fits your location. If your project specifies a stainless steel housing, review our stainless steel enclosure requirements.
In a dry chamber or main roadway of a metal mine, air-cooled dry-type construction removes oil-leak and oil-fire risks. Before locking in your site layout, Low-Voltage Mining Transformer Conditions & Documents walks through location classification and mining paperwork step by step.
KY Certificates, IP21 and IP22 Protection, and ISO Management Systems
Each KKSG mining certificate carries the KY mark and applies to the models and operating environment printed on it. KY marks China’s certificate for general-type mining electrical apparatus used in non-hazardous areas. Both certificates follow GB/T 12173-2008, an active Chinese national standard titled Mining electrical apparatus for non hazardous area. Under IEC 60529, the first IP digit (2) protects against solid objects larger than 12.5 mm and finger contact with live parts. For the second digit, IP21 on CMExC24.1859 protects against vertically falling drops. IP22 on CMExC23.1645 protects against dripping water when the enclosure is tilted up to 15°. Even with IP21 or IP22, both certificates still restrict use to non-coal mine chambers and main roadways free from dripping water and dust ingress.
| Certificate | Listed model and representative scope | Enclosure IP | Printed dates |
|---|---|---|---|
| CMExC23.1645 | KKSG-50/1.2(0.693, 0.4) and listed representative models | IP22 | 2023-10-25 to 2028-10-24 |
| CMExC24.1859 | KKSG-630/1.2(0.693) and listed representative models (KKSG-80 to 500/1.2(0.693)) | IP21 | 2025-02-17 to 2030-02-16 |
CMExC24.1859 names Zhejiang Hongmei Electrical Manufacturing Co., Ltd. as certificate holder and manufacturer, issued by the national mining-equipment testing center in Fushun. These two certificates serve as certified build examples for the listed models. If your custom KKSG project needs a KY certificate, mention it in your enquiry so our team can verify model and site coverage before production starts. Because KY is a Chinese mining certificate, verify any local approval documents your mine inspector expects before ordering.
Our company maintains ISO 9001, ISO 14001, and ISO 45001 management systems covering the production and sales of general-type mining dry-type transformers within our qualified scope. These are company management system certifications rather than product approvals; you can check KKSG model documents for full certificate details and validity dates.
How We Build and Inspect KKSG Transformers in Our Factory
We manufacture KKSG mining dry-type transformers in-house across winding, varnish impregnation, drying, core-and-coil assembly, wiring checks, and outgoing factory inspection. Our production flow begins with incoming inspection of purchased and outsourced parts before three parallel workshop tracks start.
- Coil preparation: Winding, varnish impregnation, and drying are completed in our workshop.
- Core-and-coil assembly: Prep work, core-leg stacking, coil fitting, top yoke lamination, clamping, grounding, and protection checks finish before enclosure fit-up.
- Enclosure prep and fit-up: Cleaning pre-checks followed by internal accessory pre-installation prepare the housing alongside the coil and core tracks. We then lower the core-and-coil assembly into the enclosure for leveling, sealing, wiring checks, and pre-withstand self-checks.
These tracks merge into final assembly and outgoing factory inspection before finished units enter warehouse storage. You can review the manufacturing and inspection process for the full workshop sequence. For an overview of what standard transformer routine tests check before shipment, read What Do Transformer Checks and Routine Tests Tell You?.
A Domestic Copper Mine Order We Built
We built 10 step-down transformers rated at 30 kVA (660 V to 380 V) for a domestic copper mine in China. This anonymous order record covers only the voltage conversion, capacity, and unit count, and is separate from the factory nameplate units shown in the built-capacities section.
Wood or Carton Packing and One-Year Warranty from Receipt
We pack KKSG mining dry-type transformers in wood cases or cartons for shipment. Your logistics team or forwarder can see example packing photos and handover details ahead of shipment in our guide to discuss transformer packing before dispatch.
Our KKSG units carry a one-year warranty starting from the day you receive the goods. For installation or operating questions on site, our technical team assists through remote video calls and online guidance.

Six Details to Prepare Before Requesting a KKSG Quote
We quote custom KKSG mining dry-type transformers to your exact configuration. Gathering six details from your load schedule and site plan helps us quote accurately:
- Input and output voltages: Primary feeder voltage from your mine panel and the secondary voltage your connected loads require.
- Required capacity and connection: Your load rating in kVA (or kW with power factor), plus your wiring connection if specified.
- Enclosure dimensions, material, and access: Footprint limits, housing material specs, and shaft or roadway access dimensions.
- Installation environment: Non-coal chamber or main roadway conditions, including any site moisture or dust.
- Order quantity: The number of units needed for your site or spare plan.
- Certificate requirements: Whether your project needs a KY certificate for your exact model, so we can check coverage before quoting. Confirm any local mine-inspector requirements separately in your country.
For special enclosure layouts or electrical configurations, review our custom mining transformer requirements. For a broader tender list across transformer types, see What Should You Include in a Transformer RFQ?.
Frequently Asked Questions on KKSG Mining Dry-Type Transformers
These six answers address common site, certificate, and receiving questions buyers raise before ordering a KKSG mining dry-type transformer.
Can a KKSG mining dry-type transformer be used in a coal mine or hazardous area?
No. Both KKSG certificates are issued under GB/T 12173-2008 for general-type mining electrical apparatus in non-hazardous areas. Both certificates also restrict use to non-coal mine chambers and main roadways free from dripping water and dust ingress. Coal mines and zones with flammable gas or combustible coal dust fall outside these two certificates.
Does a custom KKSG mining transformer come with a KY certificate?
Certificates CMExC23.1645 and CMExC24.1859 cover the specific models printed on them. If your order needs a KY certificate, mention it in your enquiry and we’ll verify model and site coverage before production.
What is the difference between IP21 and IP22 on the KKSG certificates?
Both IP21 (CMExC24.1859) and IP22 (CMExC23.1645) share IEC 60529 digit 2, guarding against solid objects over 12.5 mm and finger contact. For water, IP21 covers vertically falling drops while IP22 covers dripping water with the enclosure tilted up to 15°; both certificates keep their printed non-coal site limits.
Should I choose a three-phase KKSG, single-phase KKDG, or stainless-steel mining transformer?
Your choice follows your load phase and housing specification. For single-phase auxiliary circuits, check our single-phase KKDG for auxiliary loads or read Single-Phase or Three-Phase for Mining Auxiliary Loads?. If your project specifies a stainless steel housing, see stainless steel enclosure requirements.
What is the minimum order quantity, and when does the one-year warranty start?
Minimum order starts at 1 custom unit with no sample-making fee. Warranty coverage runs for one year from the day you receive the goods, supported by online guidance and remote video calls for site questions.
What should I check on the KKSG nameplate when the transformer arrives?
Match the model, rated kVA, input and output voltages, winding connection, and any applicable printed certificate number against your confirmed order. Read How to Read a Mining Transformer Nameplate for each field, and see What Do Transformer Checks and Routine Tests Tell You? for an overview of standard transformer routine tests.